This development is unique on grounds of construction methodology was adopted. The newly introduced top-down construction techniques is aimed to speed up the construction and in this case it was aimed to achieve a cycle of 7 days per floor. This is accomplished by using steel pile as columns appropriately braced at every 4 floors and the steel tube columns are pumped with concrete. The standard structural steel form work is hanged at top most floor and at every 7 days, a standard form work is drop down by operating down the bolts at 4 corners of the bay.
project details
Client
:
Sunway Group, Kuala Lumpur, Malaysia
Year of Design/Const
:
1996 - 1999
No of Floors
:
2B+GF+32 = 35 Slabs
Architect
:
AJM Architect Sdn Bhd
Scope of Work
:
Leading Structural Design
Project Status
:
Completed
Project Location
:
Petaling Jaya, Kuala Lumpur, Malaysia